888-721-8283
Well Installation & Remediation

Bremen Release Site Program

Bremen, IndianaFebruary-March 2025

Project Overview

IET performed comprehensive monitoring well and biosparge well installation services at the Bremen Release Site for Jacobs. The multi-week project included installation of 4-inch PVC wells (425 ft), 2-inch PVC sparge wells (933 ft), and a 2-inch monitoring well (35 ft), complete with IDW management, decontamination protocols, and flush surface completion.

Installation Summary

4" PVC Wells (ATV)

425 linear feet using hollow-stem augers

2" Biosparge Wells (ATV)

933.5 linear feet with specialized design

2" Monitoring Well

35 feet with flush surface completion

Support Services

IDW management (6 drums), decon pad, steam cleaning, well development

Project Details

  • Client: Jacobs (Klaudia Marzec, Tom Wiley)
  • Site: Bremen Release Site, IN
  • Completion Date: February 27 - March 31, 2025
  • Total Well Footage: 1,393.5 linear feet
  • Project Duration: Multi-week with per diem support
  • Task Order: 148062235
  • Master Agreement: 148034315
  • Total Project Value: $104,550

Learn More About Our Drilling Services