Route 60 Shell Station ISCO
Crawly, WV
February 2024
Former Gas Station
Dual-Area Treatment Strategy
Greenbrier Environmental contracted IET for a dual-area chemical oxidation program at the former Shell station on Route 60. The project treated contamination around monitoring wells MW-4 and MW-5 using activated persulfate chemistry.
$54,463
Total Project Investment
Oxidant Chemistry
Primary Oxidants
- Sodium Persulfate4,046 lbs
- Potassium Persulfate1,011 lbs
Activators & pH Control
- Ferric Oxide (Activator)1,002 lbs
- Magnesium Oxide (Buffer)412 lbs
Treatment Areas
MW-4 Area
10 injection points
MW-5 Area
7 injection points
Project Specifications
Duration
3.5 days of active injection
Total Drilling
239 linear feet with abandonment
Equipment
Probe, injection trailer, nitrogen system, forklift
Crew
3-person crew with per diem