888-721-8283

Route 60 Shell Station ISCO

Crawly, WV
February 2024
Former Gas Station
Dual-Area Treatment Strategy

Greenbrier Environmental contracted IET for a dual-area chemical oxidation program at the former Shell station on Route 60. The project treated contamination around monitoring wells MW-4 and MW-5 using activated persulfate chemistry.

$54,463
Total Project Investment
Oxidant Chemistry

Primary Oxidants

  • Sodium Persulfate4,046 lbs
  • Potassium Persulfate1,011 lbs

Activators & pH Control

  • Ferric Oxide (Activator)1,002 lbs
  • Magnesium Oxide (Buffer)412 lbs
Treatment Areas

MW-4 Area

10 injection points

MW-5 Area

7 injection points

Project Specifications

Duration

3.5 days of active injection

Total Drilling

239 linear feet with abandonment

Equipment

Probe, injection trailer, nitrogen system, forklift

Crew

3-person crew with per diem