Phase II
Continued Bioremediation Expansion

Environmental Management Inc. contracted IET for Phase II bioremediation (100-day timeframe) expanding on Phase I success. The program combined slow-release oxygen (ORC) with bacterial culture BioSlurry injections for comprehensive petroleum treatment.

$91,218
Phase II Investment
Treatment Components

ORC Points (56 locations)

Slow-release oxygen for sustained aerobic biodegradation
$35,448

BioSlurry Injections (62 points)

• 125 gallons bioslurry (nutrients + enhanced oxygen)
• 10 gallons IET's LPD (high-count Pseudomonas product)
$40,300

Infiltration Gallery

Supplemental treatment distribution
$750
Project Resources

Client

Environmental Management Inc., Springfield, IL

Microbiologist

107 hours @ $75/hr

Field Supervisor

89 hours @ $45/hr

Duration

8 days (4-person crew)

Materials

560 lbs ORC, 650 gal LPD, 350 lbs nutrients, 35 gal Hâ‚‚Oâ‚‚

Ship Date

January 28, 2003