Springfield Phase II Bioremediation
Springfield, IL
January 2003
Phase II
Continued Bioremediation Expansion
Environmental Management Inc. contracted IET for Phase II bioremediation (100-day timeframe) expanding on Phase I success. The program combined slow-release oxygen (ORC) with bacterial culture BioSlurry injections for comprehensive petroleum treatment.
$91,218
Phase II Investment
Treatment Components
ORC Points (56 locations)
Slow-release oxygen for sustained aerobic biodegradation
$35,448
BioSlurry Injections (62 points)
• 125 gallons bioslurry (nutrients + enhanced oxygen)
• 10 gallons IET's LPD (high-count Pseudomonas product)
$40,300
Infiltration Gallery
Supplemental treatment distribution
$750
Project Resources
Client
Environmental Management Inc., Springfield, IL
Microbiologist
107 hours @ $75/hr
Field Supervisor
89 hours @ $45/hr
Duration
8 days (4-person crew)
Materials
560 lbs ORC, 650 gal LPD, 350 lbs nutrients, 35 gal Hâ‚‚Oâ‚‚
Ship Date
January 28, 2003