Large-Scale Persulfate Supply Program
Mount Laurel, NJ
Aug-Oct 2017
Materials Supply
Phased Persulfate Delivery
An environmental consulting firm contracted IET for a large-scale sodium persulfate supply program delivered in two phases. This materials-only supply supported a major ISCO remediation program requiring very large quantities of chemical oxidant per shipment.
928,516 lbs
Total Persulfate Supplied
2 Phases
Phased Delivery
Phased Delivery
Phase 1 — Initial Delivery (August 2017)
• 307,806 lbs sodium persulfate
• Initial shipment (~33% of total program)
Phase 2 — Balance Delivery (October 2017)
• 620,710 lbs sodium persulfate
• Remaining shipment (~67% of total program)
Project Information
Client
Environmental Consulting Firm
Location
Mount Laurel, New Jersey
Delivery Period
August – October 2017
Technology
Sodium persulfate in-situ chemical oxidation
Scope
Materials-only supply (injection operations performed separately)
Total Quantity
928,516 lbs in two phased shipments