LMFW Facility Building 15 Utility

Houston, TX
February 2024
Utility Infrastructure
Facility Utility Investigation

Riner Engineering contracted IET for geotechnical drilling supporting Building 15 utility improvements at the LMFW facility in Houston. The project required careful coordination with active facility operations and included standby time for site access.

270 ft
Total Drilling Depth
6
Borings to 45 ft
Drilling Specifications

Primary Drilling (0-40 ft)

  • • 190 linear feet @ $16/ft
  • • Continuous Shelby tubes in top 15 feet
  • • 22 TCP tests @ $20 each

Extended Depth (40-80 ft)

  • • 27 linear feet @ $17/ft
  • • 1 TCP test @ $23

Surface Work

  • • 6 concrete/asphalt cores @ $60 each
  • • 5 patches @ $35 each
  • • 4 hours standby time
Project Details

Client

Riner Engineering (Project# 24-0007)

Completion Date

February 16, 2024

Sales Representative

Randall Cutter

Total Cost

$6,189