Large-Scale Municipal Project

Chestnut Street Groundwater Remediation

Loveland, OhioMarch-April 2023

Project Overview

IET executed one of its largest municipal remediation projects for the City of Loveland at the Chestnut Street Property. This multi-phase, month-long program completed 171 injection points with both drilling and material injection, representing a $3.1 million investment in comprehensive groundwater remediation for the community.

Project Phases

Phase 1 (March 6-15, 2023)

66 injection points completed

Phase 2 (March 16-31, 2023)

56 injection points completed

Phase 3 Final (April 1-12, 2023)

49 injection points with demobilization

Total Deployment

171 injection points across all phases

Project Details

  • Client: The City of Loveland
  • Site: Chestnut Street Property, Loveland, OH
  • Completion Date: March 6 - April 12, 2023
  • Total Injection Points: 171
  • Project Duration: 37 days
  • Total Project Value: $3,098,211
  • Contract: 2023_COL_Chestnut-001
  • PO Number: RG978952