Large-Scale Municipal Project
Chestnut Street Groundwater Remediation
Loveland, OhioMarch-April 2023
Project Overview
IET executed one of its largest municipal remediation projects for the City of Loveland at the Chestnut Street Property. This multi-phase, month-long program completed 171 injection points with both drilling and material injection, representing a $3.1 million investment in comprehensive groundwater remediation for the community.
Project Phases
Phase 1 (March 6-15, 2023)
66 injection points completed
Phase 2 (March 16-31, 2023)
56 injection points completed
Phase 3 Final (April 1-12, 2023)
49 injection points with demobilization
Total Deployment
171 injection points across all phases
Project Details
- • Client: The City of Loveland
- • Site: Chestnut Street Property, Loveland, OH
- • Completion Date: March 6 - April 12, 2023
- • Total Injection Points: 171
- • Project Duration: 37 days
- • Total Project Value: $3,098,211
- • Contract: 2023_COL_Chestnut-001
- • PO Number: RG978952