Former Dry Cleaner — Rapid Response

Madison, Indiana
60-Day Rapid Response
IET 60-day rapid response chlorinated solvent remediation at former dry cleaner in Madison Indiana treating PCE and TCE contamination with direct push injection
Project Data

Project Year

2013

Project Duration

60 days (Rapid Response)

Contaminants of Concern

PCE
TCE

Remediation Technologies Used

  • • High-Concentration Reagent Injection
  • • Multi-Phase Treatment
  • • Direct Push Technology
  • • Real-Time Monitoring

Key Results

  • Over 80% PCE and TCE reduction in 60 days
  • Measurable results after each injection phase
  • Real estate transaction proceeded on schedule
  • Continued biological activity for long-term reduction
  • Project completed within budget

Target Contaminants

PCE
TCE

Rapid Response Project

This project showcased IET's ability to deliver rapid, measurable results through an intensive 60-day remediation event.

Site Background

The site is a former dry cleaning facility in Madison, Indiana, where decades of operations resulted in significant PCE and TCE contamination in soil and groundwater. The property owner required rapid remediation to support a pending real estate transaction.

The aggressive timeline demanded an efficient, proven approach that could deliver measurable results quickly.

Remediation Strategy

IET designed an intensive 60-day remediation program combining:

  • High-concentration reagent injections for rapid contaminant destruction
  • Multiple injection events within the 60-day window
  • Real-time monitoring to optimize treatment effectiveness
  • Source zone targeting for maximum impact

The accelerated approach required careful coordination and experienced field personnel to maintain quality while meeting aggressive timelines.

Implementation

IET mobilized a dedicated field team for the 60-day event, conducting multiple injection phases with careful monitoring between each phase. The team worked efficiently to complete all planned injections while adapting the approach based on real-time results.

Direct-push technology allowed rapid deployment of treatment solutions throughout the target zone without significant site disruption.

Results

The 60-day remediation event achieved impressive results:

  • PCE and TCE concentrations reduced by over 80% within 60 days
  • Measurable results documented after each injection phase
  • Real estate transaction proceeded on schedule
  • Continued biological activity sustained long-term contaminant reduction
  • Project completed within budget despite aggressive timeline

This case study demonstrates IET's capability to deliver rapid, effective remediation when project timelines are critical.