Environmental Drilling
Highway 17 Extraction Well Installation
Mt Pleasant, South CarolinaMay 2025
Project Overview
IET completed extraction well installation services for Partner Engineering & Science along North Highway 17 in Mt Pleasant, SC. This multi-day project included soil borings, infiltration testing, and comprehensive field support over a two-day period.
Scope of Work
Soil Borings
125 linear feet of drilling for extraction well installation
Infiltration Testing
Two (2) infiltration tests performed
Project Details
- • Client: Partner Engineering & Science
- • Site: 1723 North Hwy 17, Mt Pleasant, SC
- • Completion Date: May 8, 2025
- • Total Soil Boring Depth: 125 linear feet
- • Project Duration: 2 days (including per diem support)
- • Project Manager: Nicole Soder