Environmental Drilling

Highway 17 Extraction Well Installation

Mt Pleasant, South CarolinaMay 2025

Project Overview

IET completed extraction well installation services for Partner Engineering & Science along North Highway 17 in Mt Pleasant, SC. This multi-day project included soil borings, infiltration testing, and comprehensive field support over a two-day period.

Scope of Work

Soil Borings

125 linear feet of drilling for extraction well installation

Infiltration Testing

Two (2) infiltration tests performed

Project Details

  • • Client: Partner Engineering & Science
  • • Site: 1723 North Hwy 17, Mt Pleasant, SC
  • • Completion Date: May 8, 2025
  • • Total Soil Boring Depth: 125 linear feet
  • • Project Duration: 2 days (including per diem support)
  • • Project Manager: Nicole Soder