September-October 2024
Extended Program
Dissolved Plume Treatment

Woodard & Curran contracted IET for a multi-phase groundwater remedy program targeting dissolved plume areas at the Quonset Point Facility. The project required extensive coordination, standby flexibility, and precise amendment application.

$421,750
Combined Investment (2 phases)
55,000 gal
Potable Water Used
Program Phases

Phase 1 (September 2024)

Active Days
9 days
Standby Days
10 days
Water Usage
28,000 gallons
Phase Cost
$202,700

Phase 2 (October 2024)

Active Days
11 days (dissolved) + 10 days (downgradient)
Water Usage
27,000 gallons
Treatment Areas
Dissolved + Downgradient Medium Depth
Phase Cost
$219,050
Standby Flexibility

This project required significant standby time (10 days in Phase 1) to accommodate site access, coordination with facility operations, and regulatory requirements. IET's ability to maintain readiness while managing costs was critical to project success.