Three-Day Injection Program — Progress Street, Union, NJ

30 Progress Street, Union, NJ July 15–17, 2026 Client: Provectus

At a Glance

Site Challenge

A site on Progress Street in Union needed a scheduled in situ injection event around well MW-2.

Method

Direct push drilling and injection with an injection trailer over three days, with 280 feet of drilling and borehole abandonment.

Quantities

Field days

3

Drilling / abandonment

280 ft

Crew

IET supervision + operator

Area reference

MW-2

Observed Result

The injection event was scheduled for July 15–17, 2026 and completed under one mobilization.

Limits & Caveats

The project record does not state the injected product, volumes, contaminants, or results. Performance data belongs to the client and consultant.

Scope

3-day injection event at MW-2

Drilling

280 ft

Contract Value

$30,325.00

Project Overview

IET mobilized a direct push probe, operator, injection trailer and IET supervision to 30 Progress Street in Union, New Jersey for Provectus. The event was scheduled for July 15–17, 2026 and referenced well MW-2.

The program included 280 feet of drilling with tooling allowance, 280 feet of borehole abandonment, and three days of crew per diem.

Scope of Work

  • Direct push probe and operator, 3 days
  • Injection trailer, 3 days
  • IET supervision, 3 days
  • Drilling and tooling, 280 ft
  • Hole abandonment, 280 ft

Project Details

Client

Provectus — Dixon, IL

Site

30 Progress Street, Union, NJ

Field Dates

July 15–17, 2026

Technology

In situ injection