Three-Day Injection Program — Progress Street, Union, NJ
At a Glance
Site Challenge
A site on Progress Street in Union needed a scheduled in situ injection event around well MW-2.
Method
Direct push drilling and injection with an injection trailer over three days, with 280 feet of drilling and borehole abandonment.
Quantities
Field days
3
Drilling / abandonment
280 ft
Crew
IET supervision + operator
Area reference
MW-2
Observed Result
The injection event was scheduled for July 15–17, 2026 and completed under one mobilization.
Limits & Caveats
The project record does not state the injected product, volumes, contaminants, or results. Performance data belongs to the client and consultant.
Related Services & Regional Pages
Scope
3-day injection event at MW-2
Drilling
280 ft
Contract Value
$30,325.00
Project Overview
IET mobilized a direct push probe, operator, injection trailer and IET supervision to 30 Progress Street in Union, New Jersey for Provectus. The event was scheduled for July 15–17, 2026 and referenced well MW-2.
The program included 280 feet of drilling with tooling allowance, 280 feet of borehole abandonment, and three days of crew per diem.
Scope of Work
- Direct push probe and operator, 3 days
- Injection trailer, 3 days
- IET supervision, 3 days
- Drilling and tooling, 280 ft
- Hole abandonment, 280 ft
Project Details
Client
Provectus — Dixon, IL
Site
30 Progress Street, Union, NJ
Field Dates
July 15–17, 2026
Technology
In situ injection