Downers Grove Three-Area Bio Program
Downers Grove, IL
March 2006
Petroleum Bioremediation
Multi-Component Bio Strategy
Clayton Group Services contracted IET for comprehensive three-area petroleum bioremediation combining BioInjection (LPD bacterial culture), ORC slow-release oxygen, and specialized sump treatments with enhanced bacterial loading.
$80,328
Total Investment
Treatment Areas
Area A (28 BioInjection + 25 ORC @ 10-12' BGS)
• BioInjection: 15 gal LPD + 150 gal bioslurry per point ($9,660)
• ORC: 10 lbs per point with 75 gal bioslurry ($8,625)
Total: $18,285
Area B (8 ORC + 6 Sump Injections)
• ORC: Standard 10-12' BGS treatment ($2,760)
• Sump: 110 gal LPD + 1,500 gal bioslurry per point ($4,620)
Total: $7,380
Area C (21 BioInjection + 10 ORC @ 10-12' BGS)
• BioInjection: 10 gal LPD + 150 gal bioslurry per point ($7,245)
• ORC: 10 lbs per point with 75 gal bioslurry ($3,450)
Total: $10,695
Materials Package
• ORC: 555 lbs @ $15.50/lb
• IET's LPD (Liquid Petroleum Degraders): 1,290 gallons @ $22.95/gal
• Nutrient (NutiSource): 1,500 lbs @ $2.69/lb
• Hydrogen Peroxide (35%): 50 gallons @ $19.50/gal
• Mobilization/Demobilization: $750
Project Details
Client
Clayton Group Services, Downers Grove, IL
Project Manager
Steve Swenson
Total Injection Points
98 points across three areas
Ship Date
March 28, 2006