Zionsville Three-Zone Treatment Program
Zionsville, IN
March 2018
Former DOW Site
Three-Zone Treatment Strategy
An environmental consulting firm contracted IET for comprehensive remediation of a former industrial research site. The program featured three distinct treatment zones: unsaturated EZVI, electron donor permeable reactive barrier, and downgradient Area C amendments.
Treatment Zones
Unsaturated EZVI Area (14 days)
• DPT rig, injection trailer, and crew — 14 days of continuous operations
• Material handling, supervision, per diem, and forklift included
• Nitrogen pressurized delivery system
Electron Donor PRB (10 days)
• DPT rig, injection trailer, and crew — 10 days of operations
• Material handling, supervision, per diem, and forklift included
• Nitrogen pressurized delivery
Downgradient Area C (2 days)
• DPT rig and injection trailer — 2 days targeted operations
• ZVI, electron donor substrate, nutrient, and propionate amendments
• Material handling and supervision included
Project Details
Client
Environmental Consulting Firm
Location
Zionsville, Indiana
Completion Date
March 2018
Duration
26 days on-site (14 + 10 + 2 zones)
Mobilization
Full equipment mobilization included
Technologies
EZVI, Provect-IR PRB, ZVI amendments