Durham Washington Street Investigation
Durham, NC
January 2024
Mixed Investigation
Dual-Purpose Assessment
Hart & Hickman contracted IET for a rapid assessment combining groundwater monitoring well installation with soil boring investigation at 802 Washington Street in Durham.
Monitoring Wells
3 wells
1" PVC to ~15 ft depth
Soil Borings
Several
To 10 ft with continuous sampling
Well Construction Details
- • Three groundwater monitoring wells
- • 1" PVC screens and riser construction
- • Depth to approximately 15 feet below grade
- • Flush well covers with 2' x 2' concrete pads
- • Soil cuttings spread on-site
Project Information
Client
Hart & Hickman, PC (Job No. AXR.001-001B)
Completion
January 29-30, 2024
Duration
1.25 days (rapid mobilization)
Total Cost
$4,574