Chenoa Phase I Bioremediation
Chenoa, IL
August 2002
Multi-Component Bio
Three-Technology Bioremediation
Environmental Management Inc. contracted IET for Chenoa Phase I utilizing three complementary bioremediation technologies: BioSlurry with IET's LPD bacterial culture, oxygen release compounds, and calcium peroxide injections.
$118,858
Phase I Investment
Treatment Components
BioSlurry Injections (76 points @ 6-8' BGS)
• IET's LPD (Liquid Petroleum Degrader): 10 gallons per point
• BioSlurry with nutrients and H₂O₂: 125 gallons per point
• Pretreatment fracture for pathway development
$49,400
ORC Points (66 locations)
Slow-release oxygen source for sustained aerobic activity
$41,778
Calcium Peroxide (13 points @ 8-10' BGS)
• 10 lbs calcium peroxide per point
• 50 gallons slurry with pre/post fracture
$7,800
Infiltration Gallery Treatment
Supplemental plume management
$750
Project Team & Resources
Client
Environmental Management Inc., Springfield, IL
Microbiologist
136 hours @ $75/hr
Field Supervisor
120 hours @ $45/hr
Duration
11 days (4-person crew)
Per Diem & Expenses
$280/day for 11 days
Ship Date
August 26, 2002