Chenoa Phase I Bioremediation

Chenoa, IL
August 2002
Multi-Component Bio
Three-Technology Bioremediation

Environmental Management Inc. contracted IET for Chenoa Phase I utilizing three complementary bioremediation technologies: BioSlurry with IET's LPD bacterial culture, oxygen release compounds, and calcium peroxide injections.

$118,858
Phase I Investment
Treatment Components

BioSlurry Injections (76 points @ 6-8' BGS)

• IET's LPD (Liquid Petroleum Degrader): 10 gallons per point
• BioSlurry with nutrients and H₂O₂: 125 gallons per point
• Pretreatment fracture for pathway development
$49,400

ORC Points (66 locations)

Slow-release oxygen source for sustained aerobic activity
$41,778

Calcium Peroxide (13 points @ 8-10' BGS)

• 10 lbs calcium peroxide per point
• 50 gallons slurry with pre/post fracture
$7,800

Infiltration Gallery Treatment

Supplemental plume management
$750
Project Team & Resources

Client

Environmental Management Inc., Springfield, IL

Microbiologist

136 hours @ $75/hr

Field Supervisor

120 hours @ $45/hr

Duration

11 days (4-person crew)

Per Diem & Expenses

$280/day for 11 days

Ship Date

August 26, 2002