Cleveland Supplemental ISCO
Cleveland, OH
June 2010
Supplemental Treatment
Follow-Up Oxidation Campaign
Environmental Management Specialists contracted IET for supplemental persulfate/peroxide oxidation targeting previously treated areas for enhanced contaminant destruction. This follow-up program utilized ZVI-activated persulfate with H₂O₂ enhancement.
Treatment Areas
Area #5
4,860 lbs Persulfate
398 gal H₂O₂
Area #8 (Largest)
10,953 lbs Persulfate
598 gal H₂O₂
Area #7
485 lbs Persulfate
33 gal H₂O₂
Area #12
970 lbs Persulfate
66 gal H₂O₂
Area #13
485 lbs Persulfate
33 gal H₂O₂
Project Details
Client
Environmental Management Firm
Location
Cleveland, Ohio
Total Persulfate
17,753 lbs across five areas
Duration
4 days injection trailer operations
Ship Date
June 4, 2010
Equipment
IET injection trailer, chemical mixing application