Honeywell Quanta - Coal Tar Remediation
Edgewater, NJ
March-June 2024
Coal Tar / NAPL
Program Highlights
$1.9M+
Total Project Value
59,086
Gallons Injected
4 Phases
North & South Areas
One of IET's largest groundwater remedy programs, executed across multiple phases for Jacobs Engineering on behalf of Honeywell. The project treated both North and South treatment areas with precision reagent delivery.
Treatment Phases
Phase 3a & 3b - North Area (August 2024)
North Area injection completion with borehole abandonment
7,671 gallons injected | $381,870 phase cost
Phase 4a & 4b - South Area 25% (May 2024)
Initial South Area treatment implementation
25,063 gallons injected | $744,493 phase cost
Phase 5a & 5b - South Area 50% (June 2024)
South Area treatment expansion
26,352 gallons injected | $771,369 phase cost
Project Details
Client
Jacobs Engineering (Subcontract No. 148047746)
Site Type
Industrial Facility - Honeywell Quanta
Total Duration
March - June 2024 (Multi-phase program)
Contract Structure
Lump sum + volume-based pricing with 5% retainage