Franklin PRB & Chemical Oxidation

Franklin, IN
August-September 2024
PRB + ISCO
Dual Treatment Strategy

This project combined two powerful remediation technologies: a permeable reactive barrier (PRB-1) for long-term passive treatment and in-situ chemical oxidation (ISCO) for aggressive source zone destruction.

$517,339
Total Project Investment
PRB-1 Installation

Reactive Materials

  • Provect IR (Enhanced Substrate)37,600 lbs
  • Zero Valent Iron (ZVI)4,700 lbs
Chemical Oxidation Program

Oxidant Chemistry

  • Zero Valent Iron11,057 lbs
  • Sodium Persulfate68,375 lbs
  • Hydrogen Peroxide (50%)2,984 gal
Project Details

Client

IWM (PO: $825,000)

Location

980 Hurricane Road, Franklin, IN

Equipment Duration

9 days of probe and injection operations

Approach

Combined passive PRB + active ISCO