Dual-Area Remediation
Glenville Sunoco Station Treatment
Glenville, West VirginiaJanuary 2023
Project Overview
IET completed a dual-area injection program for Greenbrier Environmental at the Glenville Sunoco Station in West Virginia. The 5.5-day project treated 33 injection points across two distinct areas (Area A: 1,237 ft², 7 points; Area B: 4,592 ft², 26 points) with 377 linear feet of hole abandonment, demonstrating efficient management of petroleum-impacted sites.
Treatment Areas
Area A
1,237 ft² coverage, 7 injection points (1.5 days)
Area B
4,592 ft² coverage, 26 injection points (4 days)
Hole Abandonment
377 linear feet with tooling wear management
Total Coverage
5,829 ft² total treatment area
Project Details
- • Client: Greenbrier Environmental (Ian Connor)
- • Site: Glenville Sunoco Station, WV
- • Completion Date: January 2023
- • Total Injection Points: 33 (Area A: 7, Area B: 26)
- • Treatment Area: 5,829 ft²
- • Project Duration: 5.5 days
- • Total Project Value: $83,485