Project Overview

IET completed a dual-area injection program for Greenbrier Environmental at the Glenville Sunoco Station in West Virginia. The 5.5-day project treated 33 injection points across two distinct areas (Area A: 1,237 ft², 7 points; Area B: 4,592 ft², 26 points) with 377 linear feet of hole abandonment, demonstrating efficient management of petroleum-impacted sites.

Treatment Areas

Area A

1,237 ft² coverage, 7 injection points (1.5 days)

Area B

4,592 ft² coverage, 26 injection points (4 days)

Hole Abandonment

377 linear feet with tooling wear management

Total Coverage

5,829 ft² total treatment area

Project Details

  • • Client: Greenbrier Environmental (Ian Connor)
  • • Site: Glenville Sunoco Station, WV
  • • Completion Date: January 2023
  • • Total Injection Points: 33 (Area A: 7, Area B: 26)
  • • Treatment Area: 5,829 ft²
  • • Project Duration: 5.5 days
  • • Total Project Value: $83,485