888-721-8283

Cherry Hill NJ Persulfate Oxidation

Cherry Hill, NJ
August 2007
$67,047
Project Overview

Chemical oxidation project for Golder Associates utilizing sodium persulfate combined with zero valent iron-mediated Fenton's reaction. The program treated two distinct areas with customized reagent formulations delivered through IET's dual-injection methodology at multiple depth intervals.

Treatment Specifications

Area A - High Intensity Treatment

10 injection points - delivered at 11-13' and 15-17' bgs in two equal injections

  • 110 lbs ZVI per point (1,100 lbs total)
  • 661 lbs persulfate per point (6,610 lbs total)
  • 55 gallons of 50% H₂O₂ per point
  • Delivered as 220 gallons of 12.5% H₂O₂ solution

Area B - Targeted Treatment

10 injection points - delivered at 11-13' and 15-17' bgs in two equal injections

  • 110 lbs ZVI per point (1,100 lbs total)
  • 125 lbs persulfate per point (1,250 lbs total)
  • 22 gallons of 50% H₂O₂ per point
  • Delivered as 100 gallons of 12.5% H₂O₂ solution
Project Totals

2,200 lbs

Total Zero Valent Iron

7,860 lbs

Total Sodium Persulfate

770 gal

H₂O₂ (50% equiv.)

Project Details

Client

Golder Associates, Inc.

Accounts Payable Contact

Cherry Hill, NJ 08034

Treatment Depths

11-17 feet bgs (dual intervals)

Completion Date

August 2007

Technology

Persulfate/ZVI/H₂O₂ ISCO

Total Injection Points

20 points