Substation Grounding Wells — Graniteville, SC
At a Glance
Site Challenge
A skid substation in Graniteville needed deep grounding wells drilled to 125 feet or refusal on bedrock.
Method
Ground rod borings with high-solids grout placed in the borings, using down-hole materials furnished by the client except grout.
Quantities
Grounding wells
2
Target depth
125 ft or refusal
Drilled footage
250 ft
High-solids grout
48 bags
Observed Result
IET completed the work in a four-day field program, July 20–24, 2026.
Limits & Caveats
Final depth reached in each well relative to bedrock refusal is not stated in the project record.
Related Services & Regional Pages
Scope
2 grounding wells to 125 ft or refusal
Footage
250 ft
Contract Value
$20,212.00
Project Overview
IET installed two grounding wells at a skid substation in Graniteville, South Carolina for Pike Electric LLC. Each well was drilled to 125 feet or refusal on bedrock.
Down-hole materials were furnished by the client with the exception of grout; IET supplied 48 bags of high-solids grout. The crew worked four days on site.
Scope of Work
- Two grounding wells to 125 ft or refusal on bedrock (250 ft of ground rod borings)
- High-solids grout, 48 bags
- Four days of crew per diem
- Single mobilization
Project Details
Client
Pike Electric LLC — Mount Airy, NC
Site
Skid Substation, Graniteville, SC
Field Dates
July 20–24, 2026
Services
Ground rod borings, grouting