Substation Grounding Wells — Graniteville, SC

Graniteville, SC July 20–24, 2026 Client: Pike Electric LLC

At a Glance

Site Challenge

A skid substation in Graniteville needed deep grounding wells drilled to 125 feet or refusal on bedrock.

Method

Ground rod borings with high-solids grout placed in the borings, using down-hole materials furnished by the client except grout.

Quantities

Grounding wells

2

Target depth

125 ft or refusal

Drilled footage

250 ft

High-solids grout

48 bags

Observed Result

IET completed the work in a four-day field program, July 20–24, 2026.

Limits & Caveats

Final depth reached in each well relative to bedrock refusal is not stated in the project record.

Related Services & Regional Pages

Scope

2 grounding wells to 125 ft or refusal

Footage

250 ft

Contract Value

$20,212.00

Project Overview

IET installed two grounding wells at a skid substation in Graniteville, South Carolina for Pike Electric LLC. Each well was drilled to 125 feet or refusal on bedrock.

Down-hole materials were furnished by the client with the exception of grout; IET supplied 48 bags of high-solids grout. The crew worked four days on site.

Scope of Work

  • Two grounding wells to 125 ft or refusal on bedrock (250 ft of ground rod borings)
  • High-solids grout, 48 bags
  • Four days of crew per diem
  • Single mobilization

Project Details

Client

Pike Electric LLC — Mount Airy, NC

Site

Skid Substation, Graniteville, SC

Field Dates

July 20–24, 2026

Services

Ground rod borings, grouting