Charlotte Commonwealth Avenue Well Installation

Charlotte, NC
January 2026
$11,000
Project Overview

Three-day direct push drilling program for Hart & Hickman, PC featuring 2-inch PVC pre-packed screen installation with professional surface completions at Commonwealth Avenue site.

Work Performed

Well Installation

  • • 185 feet of 2" PVC
  • • Pre-packed screens
  • • Annular materials
  • • 6 surface completions

Field Operations

  • • 3-day drilling operation
  • • DPT rig with 3-man crew
  • • 15% fuel surcharge applied
Project Details

Client

Hart & Hickman, PC

Sales Representative

Mike Tynan

Site Address

Commonwealth Avenue, Charlotte, NC

Completion Date

January 27-29, 2026

Job Number

CSE-002

Well Material

2" PVC with Pre-packed Screens