Charlotte Commonwealth Avenue Well Installation
Charlotte, NC
January 2026
$11,000
Project Overview
Three-day direct push drilling program for Hart & Hickman, PC featuring 2-inch PVC pre-packed screen installation with professional surface completions at Commonwealth Avenue site.
Work Performed
Well Installation
- • 185 feet of 2" PVC
- • Pre-packed screens
- • Annular materials
- • 6 surface completions
Field Operations
- • 3-day drilling operation
- • DPT rig with 3-man crew
- • 15% fuel surcharge applied
Project Details
Client
Hart & Hickman, PC
Sales Representative
Mike Tynan
Site Address
Commonwealth Avenue, Charlotte, NC
Completion Date
January 27-29, 2026
Job Number
CSE-002
Well Material
2" PVC with Pre-packed Screens