Idaho Pole Bozeman Remediation
Bozeman, MT
August 2022
Wood Treatment Facility
Major Mobilization Program
Provectus Environmental Products contracted IET for a large-scale remediation mobilization at the Idaho Pole facility in Bozeman, Montana. This project required extensive logistics including crew flights and decontamination pad construction.
2,892 ft
Total Drilling Footage
10 days
Two-Crew Operations
$202,712
First Shift Cost
Mobilization & Logistics
Mobilization Costs
- • Base mobilization: $15,000
- • Crew flights: $7,500
- • Fuel surcharge (17.75%): $2,662.50
- • Decontamination pad: $3,250
Daily Operations
- • Probe & operator: $3,800/day
- • IET injection trailer: $7,000/day
- • Supervision (2-person): $3,000/day
- • 7-person crew per diem: $2,065/day
Consumables & Support
Drilling Operations
- • Hole abandonment: 2,892 ft @ $0.95/ft
- • Tool allowance: 2,892 ft @ $2.75/ft
Equipment Support
- • Forklift rental: $495/day (10 days)
- • Material management equipment
Project Information
Client
Provectus Environmental Products, Freeport, IL
Duration
August 5-18, 2022 (Shift #1)
Crew Size
7-person crew (2 simultaneous teams)
Invoice Date
August 22, 2022