Indianapolis Three-Area Treatment

Indianapolis, IN
May 2015
Enhanced Bioremediation
Scaled Treatment Approach

An environmental consulting firm contracted IET for a three-area enhanced bioremediation program utilizing comprehensive substrate packages tailored to each treatment zone's specific requirements.

Treatment Areas

Area A (Primary Zone)

• Provect-IR: 1,300 lbs
• Zero Valent Iron: 650 lbs
• Hydrolyzed Kelp: 572 lbs
• 1.5 days operations

Area B (Main Treatment Zone)

• Provect-IR: 1,000 lbs
• Zero Valent Iron: 1,000 lbs
• Hydrolyzed Kelp: 880 lbs
• Propionate: 1,500 lbs
• 4 days operations

Area C (Targeted Zone)

• Provect-IR: 150 lbs
• Zero Valent Iron: 225 lbs
• 0.25 days operations
• Vitamin complex additions
Project Execution

Total Duration

5.75 days across three treatment areas

Equipment

Direct push probe, IET injection trailer, nitrogen system

Substrate Package

Comprehensive vitamin complex with propionate & kelp

On-Site Crew

Variable crew size optimized per area

Project Details

Client

Environmental Consulting Firm

Location

Indianapolis, Indiana

Completion Date

May 2015

Duration

5.75 days across three treatment areas