Pennsylvania Dual-Crew ISCR Program

Pennsylvania
June 2022
ISCR Technology
Dual-Crew Operations

An environmental consulting firm contracted IET for an intensive ISCR injection program at an active manufacturing facility. The project deployed two simultaneous drilling crews operating for 10 days each (20 total crew-days) to maximize efficiency and minimize site disruption.

20 days
Total Crew-Days (2 crews × 10)
Technical Challenges

Concrete Foundation Drilling

The project required specialized drilling through concrete foundations, necessitating extra trip charges and careful execution:

  • • Concrete foundation drilling through multiple foundation sections
  • • Special equipment and techniques for foundation penetration
  • • Minimal disruption to facility operations
Project Scope

Daily Operations

Drilling and remediation services over 10-day program per crew

Support Services

Chemical storage and sanitary facilities

Additional Services

  • • Off-load chemicals and material management
  • • Waste disposal of injection debris
  • • Weekend operations as needed
  • • Complete project closeout documentation
Project Details

Client

Environmental Consulting Firm

Location

Pennsylvania

Duration

10 days per crew (20 total crew-days)

Completion Date

June 2022