Pennsylvania Dual-Crew ISCR Program
Pennsylvania
June 2022
ISCR Technology
Dual-Crew Operations
An environmental consulting firm contracted IET for an intensive ISCR injection program at an active manufacturing facility. The project deployed two simultaneous drilling crews operating for 10 days each (20 total crew-days) to maximize efficiency and minimize site disruption.
20 days
Total Crew-Days (2 crews × 10)
Technical Challenges
Concrete Foundation Drilling
The project required specialized drilling through concrete foundations, necessitating extra trip charges and careful execution:
- • Concrete foundation drilling through multiple foundation sections
- • Special equipment and techniques for foundation penetration
- • Minimal disruption to facility operations
Project Scope
Daily Operations
Drilling and remediation services over 10-day program per crew
Support Services
Chemical storage and sanitary facilities
Additional Services
- • Off-load chemicals and material management
- • Waste disposal of injection debris
- • Weekend operations as needed
- • Complete project closeout documentation
Project Details
Client
Environmental Consulting Firm
Location
Pennsylvania
Duration
10 days per crew (20 total crew-days)
Completion Date
June 2022