Project Overview
IET performed comprehensive geotechnical soil boring services for Delta Oaks Group at a cell tower site in Joshua, TX. The project included Standard Penetration Testing (SPT) throughout all soil types to evaluate foundation conditions.
Our team advanced four soil borings to 20 feet with detailed SPT testing intervals, including enhanced sampling in the critical top 10 feet and provisions for rock coring if refusal conditions were encountered.
Testing Protocol
SPT Testing Strategy
- • Four (4) samples in the top 10 feet for critical near-surface data
- • Testing every 5 feet thereafter to termination depth or refusal
- • Up to 5 feet of rock coring capability if auger refusal before 20 feet
Site Support Services
- • Hand clearing and site cleanup
- • Comprehensive photographic documentation
- • Site sketch preparation
Project Specifications
- • Client: Delta Oaks Group
- • Site: Cell Tower, Joshua, TX
- • Completion Date: May 8, 2025
- • Number of Borings: Four (4) to 20 feet
- • Total Drilling Depth: 80 linear feet
- • Testing Method: Standard Penetration Testing (SPT)
- • Project Number: GEO25-25142-03