Safe Harbor Pavement Assessment
Lewisville, TX
January 2024
Pavement Project
Pavement Geotechnical Study
Colliers Engineering contracted IET for a comprehensive pavement assessment requiring continuous SPT sampling, Shelby tube collection, and complete concrete coring/patching services.
9
Borings
90 ft
Total Depth
$4,408
Project Cost
Sampling Program
Continuous SPT Sampling
31 SPT tests at 5-foot intervals for first 10 feet of each boring
Shelby Tube Samples
5 undisturbed Shelby tube samples (3" x 30") with waxing and caps
Surface Work
9 concrete/asphalt cores with complete patching restoration
Project Information
Client
Colliers Engineering (Project# 23006982A)
Completion Date
January 30, 2024
Sales Representative
Randall Cutter
Site
Safe Harbor Pavement, Lewisville