Long Lake — Geotechnical Soil Boring Program

Palestine, TX April 1–15, 2026 Client: Gerke Excavating

Total Borings

40

Total Footage

1,265 ft

Program Duration

11 Days

Contract Value

$32,980

Project Overview

IET completed a geotechnical soil boring program at Long Lake in Palestine, Texas for Gerke Excavating. The project required 40 soil borings drilled to 50-foot depth, totaling 1,265 linear feet of soil investigation.

IET deployed a buggy-mounted drilling rig to navigate the site terrain and access boring locations around the lake property. The 11-day field program was managed by Wayne McGinnis (PM) and executed by Brad Eskue's Texas team with a 2-person crew.

This project is representative of IET's geotechnical drilling capabilities across Texas, where IET regularly supports excavating contractors, engineers, and environmental consultants with subsurface investigation services.

Scope of Work

  • 40 soil borings drilled to 50 feet depth each (1,265 total linear feet)
  • Buggy-mounted drill rig deployed for site access and terrain navigation
  • 11-day field program (April 1–15, 2026)
  • 2-man crew with per diem for full program duration
  • Mobilization from IET Texas operations with full equipment package
  • Soil samples collected throughout borings per geotechnical specifications

Equipment & Resources

Drill Rig Type

Buggy-mounted geotechnical rig

Boring Depth

50 feet per boring

Number of Borings

40 borings

Total Footage

1,265 linear feet

Field Duration

11 days (April 1–15, 2026)

Crew Size

2-person field crew

Client

Gerke Excavating, Tomah, WI

IET Project Manager

Wayne McGinnis