Alpharetta Rapid ISCO Program

Alpharetta, GA
October 2010
3-Day ISCO
Rapid Deployment Chemical Oxidation

An environmental consulting firm contracted IET for a rapid 3-day ISCO program utilizing ZVI-activated persulfate with hydrogen peroxide enhancement. The project required comprehensive pre-planning including work/chemical spill plans, HASP, fire hydrant permitting, and site coordination.

Chemical Package
Sodium Persulfate (powder)25,359 lbs
Zero Valent Iron (activator)2,377 lbs
Hydrogen Peroxide (35%)1,072 gal
Project Coordination
  • • Work and chemical spill plan submittals, HASP preparation
  • • Site mobilization and vendor coordination
  • • Injection operations: trailer, probe, and vehicles (3 days)
  • • Chemical management: forklift and storage
  • • GRP geophysical study (cost-shared)
Project Information

Client

Environmental Consulting Firm

Location

Alpharetta, Georgia

Duration

3 days injection operations

Completion Date

October 2010

Special Services

Water, power washer, traffic control included