Molded Fiber Glass Facility ISCO

Solon, OhioMay 2023

Project Overview

IET completed a four-day Provect-OX chemical oxidation program for Partners Environmental Consulting at the Molded Fiber Glass manufacturing facility. The project deployed 15,071 lbs of Provect-OX reagent with bulk water delivery infrastructure for industrial site remediation.

Treatment Details

Provect-OX Reagent

15,071 lbs of chemical oxidant

Equipment Deployment

4-day IET injection trailer with probe rig

Water Infrastructure

Hydrant meter and bulk water delivery system

Logistics Support

HazMat shipping and administration services

Project Details

  • Client: Partners Environmental Consulting
  • Site: Molded Fiber Glass Facility, Solon, OH
  • Completion Date: May 2023
  • Technology: Provect-OX Chemical Oxidation
  • Total Oxidant: 15,071 lbs
  • Project Duration: 4 days
  • Total Project Value: $89,049