888-721-8283
Back to Case Studies
DrillingPiezometer InstallationInvoice #4369

NTMWD N System Pipeline — Piezometer Installation

Sherman, TX April 2026 Client: HVJ Associates

Scope

1 Piezometer — 70 ft depth

Completion Date

April 2, 2026

Contract Value

$5,293.66

Project Overview

IET installed a single 2-inch diameter piezometer to 70 feet for HVJ Associates in support of the North Texas Municipal Water District (NTMWD) N System Pipeline investigation in Sherman, Texas. The work was performed under Work Order D26-0055 (Project # DGT-23-10309.1.2), managed by PM Preston Mee.

The piezometer was completed with a flush-mount 2x2 concrete pad for long-term surface protection and regulatory compliance. The one-day field program included full mobilization from IET's Texas operations.

This project is part of IET's growing portfolio of infrastructure support drilling for municipal water system investigations across Texas.

Scope of Work

  • One (1) 2-inch diameter piezometer installed to 70 feet
  • Flush-mount 2x2 concrete pad installed at surface for protection and compliance
  • Mobilization from IET Texas operations including fuel surcharge
  • Full-day drilling rate with trained IET field crew
  • Work Order: D26-0055 | Project: DGT-23-10309.1.2

Project Details

Client

HVJ Associates North TX

End Client

North Texas Municipal Water District (NTMWD)

Site

NTMWD N System Pipeline — Sherman, TX

Work Order

D26-0055

IET Sales Rep

Brad Eskue

Project Manager

Preston Mee

Well Diameter

2 inches

Total Depth

70 feet