NTMWD N System Pipeline — Piezometer Installation
Scope
1 Piezometer — 70 ft depth
Completion Date
April 2, 2026
Contract Value
$5,293.66
Project Overview
IET installed a single 2-inch diameter piezometer to 70 feet for HVJ Associates in support of the North Texas Municipal Water District (NTMWD) N System Pipeline investigation in Sherman, Texas. The work was performed under Work Order D26-0055 (Project # DGT-23-10309.1.2), managed by PM Preston Mee.
The piezometer was completed with a flush-mount 2x2 concrete pad for long-term surface protection and regulatory compliance. The one-day field program included full mobilization from IET's Texas operations.
This project is part of IET's growing portfolio of infrastructure support drilling for municipal water system investigations across Texas.
Scope of Work
- One (1) 2-inch diameter piezometer installed to 70 feet
- Flush-mount 2x2 concrete pad installed at surface for protection and compliance
- Mobilization from IET Texas operations including fuel surcharge
- Full-day drilling rate with trained IET field crew
- Work Order: D26-0055 | Project: DGT-23-10309.1.2
Project Details
Client
HVJ Associates North TX
End Client
North Texas Municipal Water District (NTMWD)
Site
NTMWD N System Pipeline — Sherman, TX
Work Order
D26-0055
IET Sales Rep
Brad Eskue
Project Manager
Preston Mee
Well Diameter
2 inches
Total Depth
70 feet