Project Overview

IET completed a rapid two-day direct push drilling project in Pauls Valley, Oklahoma. The project involved advancing nine direct push boreholes to 25 feet and converting each to a one-inch temporary monitoring well, providing quick-turnaround groundwater assessment data for the client.

Services Performed
  • Nine direct push boreholes to 25 feet
  • Nine 1-inch temporary monitoring wells
  • Complete mobilization services
  • Daily rate for efficient project execution
Project Details
Completion Date:

October 28-29, 2025

Number of Wells:

9 temporary monitoring wells

Boring Depth:

25 feet below ground surface

Project Duration:

2 days

Client:

Atlas

Key Features
  • Rapid deployment and two-day project completion
  • Direct push technology for minimal site disturbance
  • Multiple temporary wells for comprehensive site assessment
  • Cost-effective daily rate structure