St. Louis Northeast PRB with Advanced Microbial Enhancement
St. Louis, MO
December 2019
AMR Enhanced
Advanced AMR-Enhanced Barriers
An environmental consulting firm contracted IET for a Northeast PRB expansion featuring advanced microbial remediation compound enhancement. The program included complete materials and field services for NE1 and NE3 barriers, plus materials supply for the Southern Plume treatment zone.
Treatment Components
Northeast PRB NE1 (Complete Program)
All materials and field labor included for barrier installation
Northeast PRB NE3 (Complete Program)
All materials and field labor included for barrier installation
Southern Plume Treatment (Materials Supply)
• Electron donor substrate (Provect-IR): large volume
• Zero Valent Iron: micro-scale iron powder
• Advanced Microbial Remediation (AMR) compound
• Magnesium oxide, vitamin and nutrient package
• Hydrolyzed kelp and calcium propionate electron donors
Additional Services
• Stand-by time during field operations
• Equipment storage and logistics
• Complete mobilization/demobilization
Project Details
Client
Environmental Consulting Firm
Location
St. Louis, Missouri
Completion Date
December 2019
On-Site Duration
8 days total field operations
Special Technology
Advanced Microbial Remediation (AMR) compound enhancement
Scope
Complete PRB installation (NE1, NE3) + materials supply (Southern Plume)