Enhanced Bioremediation

Eaton Facility Groundwater Treatment

Sanford, North CarolinaNovember 2025

Project Overview

IET executed a large-scale enhanced bioremediation program at the former Eaton manufacturing facility in Sanford, NC for AESI. This comprehensive project targeted both shallow and downgradient groundwater contamination using a multi-reagent approach combining Zero Valent Iron (ZVI), enhanced reductive dechlorination substrates, and specialized nutrients for aggressive biological treatment.

Treatment Approach

Provect-IR & ERD

17,568 lbs total of enhanced reductive substrates for biological treatment

Zero Valent Iron (ZVI)

7,390 lbs for enhanced reductive dechlorination

Specialized Nutrients

Vitamin B2 (52,260g), Red Yeast Rice (111,191g), Vitamin B12 (3,764g) for microbial enhancement

Chemical Additives

500 lbs each of sodium sulfite and nutrients for optimal microbial conditions

Project Details

  • Client: AESI
  • Site: Former Eaton Facility, Sanford, NC
  • Completion Date: November 2025
  • Technology: Enhanced Bioremediation with ZVI
  • Total ZVI: 7,390 lbs
  • Provect-IR: 12,500 lbs
  • Provect-ERD: 5,068 lbs
  • Project Value: $258,925
  • Sales Representative: Wade Meese