Project Overview
IET performed a dual-area persulfate injection program at the HM Royal facility in Trenton, NJ for IES Engineers. The project utilized ferric oxide-activated sodium persulfate across two treatment zones, demonstrating our expertise in activated chemical oxidation for petroleum hydrocarbon remediation.
Treatment Summary
Area A Treatment
9,519 lbs sodium persulfate + 1,380 lbs ferric activator
3-day injection with DPT rig
Area B Treatment
7,248 lbs sodium persulfate + 1,980 lbs ferric activator
3-day injection with overtime operations
Total Reagents
16,767 lbs persulfate + 3,360 lbs ferric oxide activator
Overtime Operations
10.5 hours of overtime DPT and injection crew work
Project Details
- • Client: IES Engineers Inc
- • Site: HM Royal, Trenton, NJ
- • Completion Date: June 13, 2025
- • Technology: Ferric Oxide-Activated Persulfate
- • Total Persulfate: 16,767 lbs
- • Total Ferric Activator: 3,360 lbs
- • Injection Duration: 6 days total (both areas)