Project Overview

IET completed Phase III injection services at the Wakefern Grocery facility in New Jersey for Provectus Environmental Products. The three-day project involved 135 linear feet of drilling with 9 concrete core locations, demonstrating our capability for interior building remediation with minimal disruption to ongoing operations.

Scope of Work

Concrete Coring

9 interior concrete cores for access

Drilling Operations

135 linear feet with tooling allowance

Injection Duration

3-day injection with probe rig

Equipment

IET injection trailer with supervision

Project Details

  • Client: Provectus Environmental Products
  • Site: Wakefern Grocery, NJ (Phase III)
  • Completion Date: August 4-6, 2025
  • Injection Duration: 3 days
  • Concrete Cores: 9 locations
  • Total Drilling: 135 linear feet
  • Total Project Value: $29,140