Wilmore School Phase II ESA
North Carolina
February 2024
School Property
Air Rotary Technology
Hart & Hickman contracted IET for specialized air rotary drilling at Wilmore School. The project required DPT equipment with air rotary capabilities to reach the water table efficiently.
33 ft
Air Rotary Drilling Depth
Methodology
- • Geoprobe DPT rig with air rotary capabilities
- • Hand clearance to 5 ft using decontaminated auger
- • Advanced temporary well to water table using air rotary
- • Proper abandonment following sample collection
- • IDW spread in grassy areas on-site
Project Details
Client
Hart & Hickman, PC (Job No. CDH-002)
Completion Date
February 15, 2024
Equipment
Track-mounted Geoprobe with air rotary
Total Cost
$2,606
Wilmore School Phase II ESA — Frequently Asked Questions
Answers to common questions about IET's air rotary drilling project at Wilmore School in North Carolina.
- What was the Wilmore School drilling project?
- IET performed air rotary drilling for temporary well installation as part of a Phase II Environmental Site Assessment at Wilmore School in North Carolina, contracted by Hart & Hickman.
- Why was air rotary drilling used?
- The project required DPT equipment with air rotary capabilities to efficiently reach the water table through the site's geology, where standard direct push alone could not achieve the needed depth.
- What equipment did IET deploy?
- IET used a track-mounted Geoprobe with air rotary capabilities, completed in February 2024 for the Wilmore School Phase II ESA.
- Were temporary wells installed?
- Yes. IET installed temporary wells via air rotary drilling to support Phase II ESA groundwater characterization at the school property.
- Can IET support Phase II ESA drilling for schools and sensitive sites?
- Yes. IET provides low-impact Phase II ESA drilling for schools and sensitive properties nationwide, using track-mounted and direct push equipment suited to constrained or sensitive environments.