Woodland Park Enhanced Bioremediation
Woodland Park, NJ
December 2024
Enhanced Bioremediation
Treatment Details
Provectus Environmental contracted IET for substrate injection at Area A using Provect IR technology. The treatment covered 3,750 square feet with injection depths from 7 to 25 feet below grade.
22,000 lbs
Provect IR
(Client-supplied)
12
Injection Points
3,750 ft²
Treatment Area
Project Execution
Duration
6 days (December 9, 2024)
Depth Interval
7 to 25 feet below grade
Equipment
Geoprobe, injection trailer, nitrogen system, forklift
Project Cost
$58,933
Scope of Services
- • Mobilization/demobilization
- • Geoprobe and 2-person operator team
- • IET injection trailer with nitrogen delivery system
- • Supervision (2-person crew)
- • Borehole abandonment (450 linear feet)
- • Per diem for 3-person crew
- • Forklift rental for material management
- • Tooling allowance