Mooresville Temporary Well Project

Mooresville, NC
January 2024
DPT Drilling
Project Overview

GeoHydro Engineers contracted IET for rapid direct push technology (DPT) installation of six temporary monitoring wells to support environmental assessment activities.

6
Temporary Wells
225 ft
Total Well Depth
1 day
Completion Time
Well Construction
  • • Six temporary monitoring wells to approximately 45 feet depth
  • • 1" PVC screen and riser construction
  • • Proper annular materials and sealing
  • • Complete abandonment upon sampling completion
  • • Soil cuttings spread on-site
Project Details

Client

GeoHydro Engineers (Project 231926.31 Task 30)

Project Manager

Chris Devne, PG

Equipment

DPT rig with 2-person crew

Total Cost

$5,671