DrillingBarge DrillingInvoice #4450

Barge Drilling Investigation — Waco, TX

Waco, TX May 2026 Client: HVJ Associates

Scope

3 Borings to 80 ft — Barge Platform

Field Period

May 18–29, 2026 (7 barge days)

Contract Value

$107,412.00

Project Overview

IET executed a specialized barge drilling investigation at Waco, Texas for HVJ Associates (Proj# DG23-10037.1), managed by PM Preston Mee. The program required full crane and barge mobilization, with three (3) deep borings drilled to 80 feet from the barge platform over 7 operational days.

Barge mobilization and crane/barge setup was completed May 18–19, with barge boring B-5 work executed May 20–22 and May 26–29. The project included comprehensive marine insurance for the full project duration.

This project demonstrates IET's unique capability to deploy fully equipped barge drilling platforms for over-water investigations — a critical service for bridge, dam, waterway, and infrastructure projects across Texas where conventional land-based drilling is not feasible.

Scope of Work

  • Three (3) borings to 80 feet depth from barge platform
  • Full crane and barge mobilization/setup (May 18–19)
  • 7 barge/crew operational days at $9,250/day
  • Marine insurance coverage for full project duration
  • Boring B-5 completed over multiple operational days (May 20–29)
  • Managed by PM Preston Mee | Sales Rep: Brad Eskue

Project Details

Client

HVJ Associates North TX — Dallas, TX 75247

Site

Barge Drilling — Waco, TX

Project Number

DG23-10037.1

IET Sales Rep

Brad Eskue

Project Manager

Preston Mee

Number of Borings

3

Boring Depth

80 feet (water-based)

Barge Days

7 operational days