South Cedar ISGS Remediation
Tacoma, WashingtonJune 2025
Project Overview
IET executed an In-Situ Generated Solidification (ISGS) remediation program at 3133 South Cedar in Tacoma, WA for Landau Associates. The six-day injection program utilized 23,112 lbs of ISGS amendment material with complete neutralization services, demonstrating our expertise in ISGS technology deployment on the West Coast.
Treatment Details
ISGS Amendment
23,112 lbs of amendment material for soil stabilization
Neutralization Services
Complete post-injection neutralization for environmental compliance
Equipment Deployment
IET injection trailer with supervision and forklift support
Project Duration
6 days of injection operations
Project Details
- • Client: Landau Associates, Inc.
- • Site: 3133 South Cedar, Tacoma, WA
- • Completion Date: June 9, 2025
- • Technology: In-Situ Generated Solidification (ISGS)
- • ISGS Amendment: 23,112 lbs
- • Injection Duration: 6 days
- • Project Number: 2238001.010.015.051